Apartment Renovation in Rome: Complete Step-by-Step Guide

February 10, 20259 min read
Apartment Renovation in Rome: Complete Step-by-Step Guide

Renovating an apartment in Rome is an exciting but complex project. With over 500 completed renovations, Edilquadro guides you step by step through every phase of the process.

Phase 1: Design and Site Survey

Everything starts with a free site survey at your apartment. Our technicians assess the property's condition, listen to your needs, and propose customized solutions. In this phase we define the layout, space distribution, materials, and preliminary budget.

Phase 2: Permits and Paperwork in Rome

For a complete renovation in Rome you need a CILA (Certified Start of Works Communication), to be submitted to the relevant Municipality. Our technical office prepares all necessary documentation, including the qualified designer's technical report. Preparation takes approximately 7-10 days.

Phase 3: Demolition and Preparation

Demolition includes removing existing floors, partitions to be modified, old systems, and wall coverings. This is an important phase that requires care to avoid damaging load-bearing structures. Average duration: 3-5 working days for an 80-100 sqm apartment.

Phase 4: Electrical and Plumbing Systems

Complete system renovation is essential for safety and comfort. CEI-compliant electrical system with differential switch, LED light points, integrated USB outlets. Plumbing with multi-layer pipes, manifolds, and thermostatic mixers. Duration: 5-7 days.

Phase 5: Screeds and Flooring

After systems installation, leveling screeds are laid and flooring is installed. Porcelain stoneware, parquet, resin: each material has different installation times. For a standard apartment, this phase requires 7-10 working days including drying times.

Phase 6: Bathrooms and Finishes

Installation of sanitary ware, bathroom tiling, interior doors, skirting boards, and various finishes. This is the phase where the apartment takes its final shape. We schedule 5-7 days for this phase.

Total Timeline

A complete apartment renovation in Rome takes an average of 45-60 working days. Edilquadro respects the timelines agreed in the contract, with penalties at our expense in case of delays. Contact us for a detailed quote and customized timeline.

Author

Stylianos Kountalis

Founder of Edilquadro — Construction company in Rome since 1998. Specialized in residential and commercial renovations with over 500 completed projects.

Want to bring your project to life?

Contact us for a free site visit and detailed quote.

🍪 We use cookies

We use cookies and similar technologies to improve your experience, personalize content, analyze traffic and show you relevant ads.

Privacy PolicyCookie Policy